A network of nearly twenty injection points was established and Enviro-BAC was injected in a liquid slurry through the groundwater sampling rods of a Geoprobe Drill Rig. A sampling event conducted 60 days post injection revealed dramatic reductions throughout the groundwater plume. Concentrations of all detected targeted compounds were reduced more than 85%. Based on the immediate reductions in petroleum products the site immediately met criteria for regulatory closure. Continued quarterly sampling indicated further reductions and no rebound as seen with our chemical only products.